NGCP SCHEDULED POWER INTERRUPTION
May schedule ulit si NGCP! This time, marami silang activities sa mga 69kV lines segments nila. Narito ang mga oras ng interruption ni Beshy NGCP:
DATE:
December 7, 2023, Thursday
TIME:
6:00 am–8:00 am
6:00 pm–7:00 pm
AFFECTED AREAS:
ALL BARANGAYS OF: Guimba, Sto. Domingo, Science City of Munoz, Licab, Lupao, Talugtug
TALAVERA: all barangays (except portion of San Miguel na Munti)
QUEZON: all barangays (except San Andres 1 & 2)
ALIAGA: Sunson, Betes, San Carlos
LLANERA: Casile
~~~
TIME:
6:00 am–7:00 pm
AFFECTED AREAS:
ALIAGA: all barangays (except Suson, Betes and San Carlos)
TALAVERA: Portion of San Miguel na Munti
QUEZON: San Andres 1 & 2
CARRANGLAN: all barangays & Conversion, Pantabangan
REASON:
Isolation of CB04(5LI1CBN-FLO)CBN, CBN-SPA 69kV Line Segment, TUA-BUK 69kV Line Segment and BUK-FLO 69kV Line Segment to facilitate the
following:
• To implement Wood pole Replacement Program along Cabanatuan-Fatima 69kV line.
• Electrical testing of HVEs.
• Preventive/Corrective maintenance in substation and TL.
• Replacement of test switch of NEECO-2 Lupao SS.
Note: Some connected loads of SPA-TUA 69kV line segment will be shifted to Cabanatuan – San Luis 69 kV Line, NGCP Engineer On Duty will provide clearance before customer’s switching activities to avoid overloading